Cities

Cabinet approves 8.4 km Aqua Line metro extension from Noida to Greater Noida

Five elevated stations will link Sector-51 to Greater Noida Sector-04.

An elevated metro viaduct in Noida
File photo: A metro viaduct at Noida Sector 18, on the Blue Line that the Aqua Line connects to. Photo: Kool Nerd 123 / Wikimedia Commons, CC BY-SA 4.0

The Union Cabinet on Wednesday approved an extension of the Noida Metro’s Aqua Line from Noida Sector-51 to Greater Noida Sector-04. Prime Minister Narendra Modi chaired the meeting.

The 8.449 km corridor will have five elevated stations and will connect with the Blue Line at Noida Sector-61. The Blue Line is part of the Delhi Metro, so the interchange gives a rail link towards Delhi.

Once it opens, Noida and Greater Noida will have 71.878 km of working metro lines. By our calculation from the two official figures, that puts the present network at about 63.4 km.

The government’s release did not give the project’s cost or a completion date. The news agency PTI reported the estimated cost as ₹2,390 crore.

The Aqua Line today runs 29.7 km between Noida Sector-51 and the Depot station in Greater Noida, with 21 stations, 15 of them in Noida and six in Greater Noida, according to the International Railway Journal. It opened on 25 January 2019 and is run by the Noida Metro Rail Corporation.

The extension is shorter than the plan Uttar Pradesh cleared two years ago. In November 2024 the state cabinet approved a 17.435 km line from Sector-51 to Knowledge Park V in Greater Noida, with 11 stations, at a cost of ₹2,991.60 crore, Business Standard reported then. The first five stations on that list were Noida Sectors 61, 70, 122 and 123 and Greater Noida Sector 4. The Union Cabinet release names only Sector-51, the Sector-61 interchange and Greater Noida Sector-04. It does not say what happens to the stretch beyond Sector-04.

Under the 2024 plan, the Centre and the state government were each to put in ₹394 crore, with the rest coming from the Noida and Greater Noida authorities in a 40:60 split, NewsX reported. That plan projected about 1.25 lakh passengers a day for the full 17.435 km line. No comparable figures have been published for the shorter extension approved this week.

For residents, the release lists the places the line is meant to serve. They include Gaur City 1 and 2 in Greater Noida Sector-04 and Cleo County in Sector-122. It names Gaur City Mall, Blue Sapphire Mall, IKEA in Sector-51 and Anthurium Mall in Sector-73. Offices on the list include Tech Mahindra and TCL Tech in Sector-60. It also names Delhi Public School in Sector-122 and the Kailash, Rama and Cloud9 hospitals.

The government said the line would cut road congestion and carbon emissions and improve access to Delhi’s airport, railway stations and bus depots. These are the government’s stated expectations. Mr Modi wrote on X: “As Noida and Greater Noida grow, why should daily commutes become longer?” He added: “Less congestion. Shorter commutes.”

The release does not say when construction will start or when trains will run. It does not say how the cost will be shared between the Centre, the state and the Noida and Greater Noida authorities. It does not name all five stations.

Length8.449 km
Stations5, all elevated
InterchangeBlue Line at Sector-61

Source ledger · स्रोत खाता

Each fact in this story, where it came from, and how it was checked.

FactSourceCheck
Cabinet approved the extension on 11 Nov 2026Press Information BureauConfirmed, official source
8.449 km, five elevated stations, Blue Line interchange at Sector-61Press Information BureauConfirmed, official source
Network will reach 71.878 kmPress Information BureauConfirmed, official source
Cabinet meeting was chaired by PM Narendra ModiPress Information BureauConfirmed, official source
Sector-61 interchange is with the Delhi Metro Blue LineBusiness Standard (2024), India BloomsConfirmed, independent outlets
Present network about 63.4 km (71.878 minus 8.449)Our calculation from the two official figuresConfirmed, official source
Estimated cost ₹2,390 crorePTI (The Week), Outlook IndiaConfirmed, independent outlets
Existing Aqua Line: 29.7 km, 21 stations (15 Noida, 6 Greater Noida), Sector-51 to DepotInternational Railway Journal; Outlook India (2019) for length and stationsConfirmed, independent outlets
Aqua Line opened 25 January 2019; operated by Noida Metro Rail CorporationOutlook India (2019)Single source
UP cabinet in Nov 2024 approved 17.435 km Sector-51 to Knowledge Park V line, 11 stations, ₹2,991.60 croreBusiness Standard, NewsXConfirmed, independent outlets
First five stations in the 2024 plan: Noida Sec-61, 70, 122, 123 and Greater Noida Sec-4Business Standard, NewsXConfirmed, independent outlets
2024 plan funding: Centre ₹394 crore, UP ₹394 crore, rest from Noida and Greater Noida authorities 40:60; projected ridership about 1.25 lakh a dayNewsXSingle source
Places served: Gaur City 1 and 2, Cleo County, Gaur City Mall, Blue Sapphire Mall, IKEA (Sec-51), Anthurium Mall (Sec-73), Tech Mahindra and TCL Tech (Sec-60), DPS Sec-122, Kailash, Rama and Cloud9 hospitalsPMIndia copy of the Cabinet release; PTIConfirmed, official source
Government expects less congestion, lower carbon emissions, better access to Delhi’s airport, railway stations and bus depotsPress Information BureauConfirmed, official source
Modi on X: “As Noida and Greater Noida grow, why should daily commutes become longer?” and “Less congestion. Shorter commutes.”India Blooms, Outlook IndiaConfirmed, independent outlets
Release gives no construction start, funding split or full station listPress Information BureauConfirmed, official source

Corrections to this story: none.